Hello Dave,
=days360("01/07/2012",now())
Should do it.
Best wishes
Dave Wisnia
In message <52bb25d3c0dave@triffid.co.uk>
Dave Symes <dave@triffid.co.uk> wrote:
> SARPC RO 6.20 and Eureka Spreadsheet.
> I've been messin' trying to get the spreadsheet to automatically do
> something and can't get it to function how I want, so I'm hoping someone
> here might have the solution.
> It's to do with aged debts. (Customers who owe me lolly)
> I want to enter a date in cell A10 of say 1/July/2012 (That's no problem,
> entering dates or times and formatting them) what follows is the problem...
> In cell D10 I want some auto means of displaying the amount of time that
> has passed to now the 6th of August 2012
> Obviously tomorrow when run it needs to display the new amount of time
> passed. (I am aware of the NOW() function but can't get it to do anything
> meaningfull).
> In other words when I run the sheet, I want that cell to tell me day by
> day, how many months or days have passed since the 1st of July.
> Would appreciate the help.
> Dave
--
With very best wishes
Dave Wisnia
Back to comp.sys.acorn.misc | Previous | Next — Previous in thread | Next in thread | Find similar
Eureka spreadsheet question. Dave Symes <dave@triffid.co.uk> - 2012-08-06 20:49 +0100
Re: Eureka spreadsheet question. Dave Wisnia at home <david@wisnia.net> - 2012-08-06 21:53 +0100
Re: Eureka spreadsheet question. Dave Symes <dave@triffid.co.uk> - 2012-08-07 06:48 +0100
Re: Eureka spreadsheet question. Dave Wisnia at home <david@wisnia.net> - 2012-08-07 09:02 +0100
Re: Eureka spreadsheet question. M Harding <riscos@mdharding.org.uk> - 2012-08-07 11:22 +0100
Re: Eureka spreadsheet question. Dave Wisnia at home <david@wisnia.net> - 2012-08-07 12:33 +0100
Re: Eureka spreadsheet question. Dave Symes <dave@triffid.co.uk> - 2012-08-07 20:04 +0100
Re: Eureka spreadsheet question. Brian Debenham <brian@bdebenham.co.uk> - 2012-08-06 22:01 +0100
Re: Eureka spreadsheet question. Dave Symes <dave@triffid.co.uk> - 2012-08-07 06:37 +0100
Re: Eureka spreadsheet question. Dave Symes <dave@triffid.co.uk> - 2012-08-14 19:51 +0100
Re: Eureka spreadsheet question. Dave Wisnia at home <david@wisnia.net> - 2012-08-14 22:35 +0100
Re: Eureka spreadsheet question. Dave Symes <dave@triffid.co.uk> - 2012-08-15 07:11 +0100
Re: Eureka spreadsheet question. Tony Moore <old_coaster@yahoo.co.uk> - 2012-08-15 10:42 +0000
Re: Eureka spreadsheet question. Alan Calder <alan_calder@o2.co.uk> - 2012-08-15 13:34 +0100
Re: Eureka spreadsheet question. John Bryan <john@bryan86.fsnet.co.uk> - 2012-08-15 14:30 +0100
Eureka spreadsheet question. Dave Symes <dave@triffid.co.uk> - 2012-08-15 21:43 +0100
Re: Eureka spreadsheet question. Dave Symes <dave@triffid.co.uk> - 2012-08-18 19:06 +0100
Re: Eureka spreadsheet question. Julian Fry <julainfry@tiscali.co.uk> - 2012-08-19 13:18 +0100
Re: Eureka spreadsheet question. Dave Symes <dave@triffid.co.uk> - 2012-08-19 15:16 +0100
Re: Eureka spreadsheet question. Dave Symes <dave@triffid.co.uk> - 2012-08-19 15:18 +0100
csiph-web